|  Case
            Study Raising
            the roof of the Chunju/Jeonju sports stadium
              global modelling of stadium roof structuredevelopment of cable stay tensioning sequencelinear analysis 
 Tony Gee & Partners were retained by steelwork fabricator/erector Hanmaek Heavy Industries Co Ltd
            to provide a full erection analysis of the 260m x 160m roof
            structure of the 42,000 seat Chunju/Jeonju sports stadium, one of 11 new stadiums
            being constructed in Korea for the 2002 football World Cup. TGP's
            brief was to define the cable prestressing sequence and the values of prestress to be used
            at any given time. The aim was to be able to predict on site and in advance the effect
            that tensioning any one cable, or pair of cables, would have on any other cable. TGP chose to use
            LUSAS Civil & Structural analysis to help model the construction process
            and built a LUSAS model of the complete roof structure
            including masts and stays. 
 Chunu/Jeonju stadium has a
            steel roof comprising a perimeter truss supported on A-shaped columns to the rear of the
            grandstand and an inner ring truss supported via a fanned cable network on four, 63m high
            masts. Because all cable stays have an influence on all other cables
            attached to that mast the sequence of stressing the cables and raising the roof from its
            erected position was of vital importance to achieve both the correct roof shape and to
            avoid any unacceptable locked in stresses.   To simplify the modelling of the 20000 sq. m. space frame roof, models
            of individual roof trusses were created to provide equivalent section properties for a
            single beam element for use in the main model. Bar elements modelled the cable stays.
            Pinned supports were used at the base of the masts. Spring supports modelled the
            supporting columns of the pre-cast concrete grandstand around the perimeter. Plain
            vertical supports were used at each of the 32 trestle positions where lift-off would
            occur. Whilst a nonlinear analysis with lift-off joints could have been carried out
            considering catenary effects TGP made a conscious decision to perform a linear analysis
            and evaluate support lift-off by using an inspection method. As final tensions are
            approached the cable extensions approach the modelled linear behaviour.
             
              
                
                  | At each mast 7 cables support the free edges of adjacent roof sections (4 on
            the long section, 3 on the shorter section). In addition, 4 cables arranged in a diamond
            shape in the plane of the cross beam between adjacent roofs, anchored at the same position
            as a pair of cables from the ring truss, together with another pair going out from the
            roof to the branch beam at the rear of the mast stabilise it laterally. Cables used are
            typically of 65mm and 95mm diameter. The main rear guy at a mast consists of 6, 100mm
            diameter cables and carries in excess of 1000 tonnes. | 
 |  A key part of the analysis was to investigate whether progressive
            tensioning all of the cables in one corner could be achieved without affecting other
            cables in other corners prior to moving to another corner to repeat the sequence. This had
            obvious construction benefits in avoiding the need to move the tensioning equipment around
            the site. To test for this, temperature loadings were applied to model the tensioning of
            each cable individually. Also, as a check, a unit load was applied to each cable in turn
            to see what tensions and compressions it put into other cables (for one corner only). From
            these results a matrix was produced which could then be solved for any cable tensioning
            sequence.
             
              
                
                  | David
            Barnes, Associate at TGP, explains: 'We looked at each cable in turn because you could
            work out what the effect of stressing two cables at once would be by adding the columns in
            the matrix together. A unit load was applied to each cable at one corner to work out what
            effects that had on all other cables in that corner. We also looked at whether tensioning
            one corner would have any effects on cables in the other corners and found that the load
            transfer was negligable (less than 2.5%). Therefore the 3D unit in each corner was
            effectively self contained and could be stressed independently of the others.' | 
 |  The inner ring truss is so stiff 
            that the cables fanning out from
            the corner do progressively less and less work and the longest cable is almost
            architectural in nature. As a result, tensioning the main load-carrying
            cables cables in the corner slackens off the wide fanning cables and leads to a continual
            change of tensions throughout the cable system. The permanent works designer had given TGP
            a set of final cable tensions that had to be obtained on site and the matrix was solved to
            achieve these. Simon Dimmock, engineer on the project said: 'In tensioning the cables on
            site we were always going to have a situation where the last cable to be tensioned would
            affect all the others, so we had to know what that effect was in
            advance - hence the use of LUSAS'. Multiple LUSAS analyses were carried out starting with the roof sitting
            on the trestles with no cable tension, before increasing the tension in two cables at a
            time up to 25% tension. After all cables had reached this level of tension the sequence
            was repeated using tensions of 50%, 75%, 90% and finally using 100% of the tension
            supplied by the permanent works designer. This tensioning sequence was used by Tony Gee &
            Partners on site. Because of the linear analysis approach and the absence of modelling the
            catenary effects the response of tensioning the cables on site to 25% of final tension did
            not reflect the response suggested in the LUSAS model. Later tensioning to 90% and above
            matched the LUSAS model far better. The philosophy of the permanent works design was that
            once the correct tensioning was applied the roof would simply lift off the trestles -
            which it did. Using LUSAS, lift off was estimated to occur at between 80-90% of final
            tension and in fact the corner lifted off very slightly before that. Whilst TGP was not
            doing a third party check, the process of creating a separate computer model with LUSAS
            and having the roof lift off the trestles when the tension specified by the permanent
            works designer was input, effectively corroborated their work. 
 "In tensioning the cables on
            site we were always going to have a situation where the last cable to be tensioned would
            affect all the others, so we had to know what that effect was in
            advance - hence the use of LUSAS."  Simon Dimmock,
          Project Engineer, Tony Gee & Partners 
 Find out more  
  Other LUSAS Civil &
          Structural case studies:  |