Bridge analysis, design + assessment

Case Study 

Share this article 

 

Analysis and Design of Avenues Walk Flyover

  • Detailed 3D analysis of one of the longest and most highly curved single span girder bridges in the world

  • Investigation of lower lateral bracing requirements

  • Uplift analysis for deck pour sequence

Avenues Walk Flyover

Avenues Walk Flyover is a single-span curved girder bridge that spans the Florida East Coast Railroad to provide access to a private mixed use development on a restricted site south of Jacksonville. GAI Consultants used LUSAS Bridge analysis software for detailed 3D analysis and comparison checking of the structure, and notably to investigate lower lateral bracing options and to provide a means of reducing uplift during a slab pour construction sequence.

Overview

Avenues Walk Flyover provides access to a triangular-shape mixed-use development site bounded on two sides by Interstate 95 and the Florida East Coast Railroad.

The bridge alignment was essentially dictated by the grade required for the access road to rise sufficiently within the land space available in order to meet a specified railroad clearance. The severe curvature and length of the resulting bridge required the development of innovative design and construction methods to meet both geometric and economic restraints. GAI’s eventual solution, with a span length of 218’, a width of 79’ and a centerline radius of 300’, means that Avenues Walk Flyover is one of the longest and most highly curved single span girder bridge structures in the world.

Site (red outline) accessed by Avenues Walk Flyover

To achieve the combination of span and curvature for this bridge required unique design elements in order to optimize capacity and ensure stability. Varying end skews, non-uniform girder spacings and girder depths, lower lateral girder bracing, uplift resistant bearings, a 32 ton concrete counterweight, and a transversely staged deck pour would all end up being incorporated into the final design.

Initial and re-designed bridge alignments and final single deck solution

Bridge development

Concept designs looked at a single-span and a three-span option, with the lower cost single-span option being preferred by the developer. For this, separate 37’ wide, single-span eastbound and westbound structures were initially proposed but the potential for uplift on these separate, narrow, and highly curved structures resulted in one single 73’ wide structure of greater stability being chosen. Further investigations into different skew arrangements and relative stability/uplift issues for this wider structure resulted in a final solution which used parallel end supports, one radial with some potential for uplift, and the other skewed to the roadway at about 45 degrees. To support the deck, eight centrally placed, equally spaced girders were proposed, but from analysis carried out it was found that, because of the severe curvature of the deck, the two girders on the outside edge were carrying four to five times more moment than the innermost girder. This caused GAI to move the set of girders more toward the outside of the curve, reducing the deck overhang. This gave a beneficial 10 percent reduction in load distribution for the most heavily loaded girder. Girder spacing was also adjusted. Spacing for the two outer, 120” deep girders was decreased from a fixed 9’-5” to 8’-0”, and the five inner, 104” deep, girder spacings were increased to 10’-0”. The 300’ centerline radius on the bridge required a 4% superelevation, making the outside curb line almost 34 inches higher than the inside curb line. Because of this, the outside girders, which are only 16” deeper than the inside girders, do not control the under-clearance, so by using shallower girders for the inner six locations, ten valuable inches of overall bridge height were saved.

Avenues Walk Flyover showing falsework towers

Analysis and design

In order to verify the bridge’s behaviour during both erection and in-service loading both grid and finite element analysis software was used. 2D grid analysis was employed essentially as a ‘framework’ tool for overall girder design, flange plate optimization, diaphragm design, and bearing design. 3D finite element analysis with LUSAS Bridge was used for detailed design to make sure that 3D effects were being accounted for in the individual bridge elements - something not possible with a grid analysis. Using LUSAS, dead load effects were assessed and final construction deflections were derived. Live loading was analysed for each vehicle lane with combinations and envelopes producing worst-case values. LUSAS was also used investigate bearing stiffnesses, lower lateral bracing loading, and to assess potential uplift from transverse deck pour sequences. A final analysis of the complete proposed design was carried out by a third party to verify the results obtained.

LUSAS 3D modelling of Avenues Walk Flyover showing vehicle loading to inner lane

LUSAS 3D modelling of Avenues Walk Flyover showing vehicle loading to inner lane

 

Lower lateral bracing

Using LUSAS Bridge, GAI investigated lower lateral bracing options to carry wind and lateral stresses in the plane of the girder bottom flange. Three arrangements were examined; lateral bracing in both exterior bays and one internal bay, lateral bracing in the exterior bays only, and lateral bracing in the outside girder bay only. Based on some preliminary analysis, it was determined that final condition lateral deflections and stresses were not large enough in the innermost girders to warrant the cost of installing lateral bracing in that bay. In the erection condition, however, the use of lower lateral bracing would have had an impact on the magnitude of lateral deflection if the interior girders were erected first. Since the planned construction sequence was to erect the outside girder pair first, the potential advantage of lateral bracing would not, in fact, be realized. The final design included a single bay of lower lateral bracing, placed between the two outermost girders.

Lower lateral bracing to the two outer girders

Deck pour sequence analysis

The steel frame was erected on two falsework towers. However, prior to the deck placement, the towers were removed. As a result, uplift, calculated to be caused by pouring the deck, had to be overcome. With the entire steel frame in place to resist the effects of overturning, a concrete counterweight weighing 32 tons was placed adjacent to the inside edge girder at the radial abutment to reduce any uplift forces. Additionally the deck was placed in two transverse deck sections with the deck over the four innermost girder lines placed first. After the deck cured, the remaining section of the deck was placed, with the first pour acting as a counterweight. The bridge was constructed using uplift resistant bearings and uplift resistant foundations at the inside edge of the radial abutment so that there was adequate capacity for the entire uplift including live load effects shown in the worst-case analysis model.

From analyses, mid-span dead load deflections were calculated and compared for each girder. After the removal of the falsework towers the calculated deflection for the outermost girder varied from 10.8 inches in the LUSAS 3D finite element model to 13.4 inches in the 2D grid analysis model, a variation of about 25 percent. This difference would be largely due to the limitations of grid analysis to include lateral bracing effects. The models showed good agreement regarding the end reactions and the uplift potential at the radial abutment. For the maximum downward reaction case at the outermost girder the models all agreed within 2 percent.

Samuel N. Spear, engineer at GAI Consultants said: “LUSAS proved to be a valuable tool for the project. We especially enjoyed the ability to model the various stages of construction and in-service loading. He was also complimentary of the LUSAS support staff: “When we required modelling assistance the LUSAS support staff were helpful in answering our questions when the need arose”.

Avenues Walk Flyover Project Stakeholders

  • Owner: City of Jacksonville, Florida

  • Engineer: GAI Consultants, Inc.

  • Contractor: Hal Jones, Inc.

  • Railroad: Florida East Coast RR

  • Developer: KIMCO Developers, Inc.


“LUSAS proved to be a valuable tool for the project. We especially enjoyed the ability to model the various stages of construction and in-service loading... and when we required modelling assistance the LUSAS support staff were helpful in answering our questions when the need arose”

Samuel N. Spear, GAI Consultants

 


Find out more: 

Dominic Bagley
LUSAS Regional Manager.

Email: dominic.bagley@lusas.com


Share this article 


Find out more

LUSAS Bridge

Software products

Software selection

 


 

Other LUSAS Bridge case studies:

Software Information

  Bridge / Bridge plus
green_arrow.gif (94 bytes) Software overview
green_arrow.gif (94 bytes) Modelling in general
green_arrow.gif (94 bytes) Advanced elements, materials and solvers
green_arrow.gif (94 bytes) Load types and combinations
green_arrow.gif (94 bytes) Staged construction modelling
green_arrow.gif (94 bytes) Geotechnical / Soil-structure modelling
green_arrow.gif (94 bytes) Analysis and design
green_arrow.gif (94 bytes) Design code facilities
green_arrow.gif (94 bytes) Viewing results
green_arrow.gif (94 bytes) Software customisation

  Bridge LT
green_arrow.gif (94 bytes) Software overview

  Choosing software
green_arrow.gif (94 bytes) Software products
green_arrow.gif (94 bytes) LUSAS Bridge LT
green_arrow.gif (94 bytes) LUSAS Bridge
green_arrow.gif (94 bytes) LUSAS Bridge Plus
green_arrow.gif (94 bytes) Software selection
green_arrow.gif (94 bytes) Software options

green_arrow.gif (94 bytes) Videos
 
green_arrow.gif (94 bytes) Case studies

  Application areas
green_arrow.gif (94 bytes) Footbridge design
green_arrow.gif (94 bytes) Movable structures
green_arrow.gif (94 bytes) Rail solutions
green_arrow.gif (94 bytes) Arch bridges
green_arrow.gif (94 bytes) Major crossings
green_arrow.gif (94 bytes) Soil-Structure Interaction Modelling

  Additional information
green_arrow.gif (94 bytes) Linear and nonlinear buckling analysis
green_arrow.gif (94 bytes) Curved girder analysis
green_arrow.gif (94 bytes) Integral or jointless bridges
green_arrow.gif (94 bytes) Post-tensioning
green_arrow.gif (94 bytes) Concrete modelling
green_arrow.gif (94 bytes) Interactive Modal Dynamics
green_arrow.gif (94 bytes) LUSAS Programmable Interface (LPI)

  General information
green_arrow.gif (94 bytes) Hardware specification
green_arrow.gif (94 bytes) Licencing and Networking options
green_arrow.gif (94 bytes) Software prices
green_arrow.gif (94 bytes) Documentation
green_arrow.gif (94 bytes) Links page
 

Request information

 


innovative | flexible | trusted

LUSAS is a trademark and trading name of Finite Element Analysis Ltd. Copyright 1982 - 2022. Last modified: August 25, 2023 . Privacy policy. 
Any modelling, design and analysis capabilities described are dependent upon the LUSAS software product, version and option in use.