Case Study
Share this
article
Analysis and Design of Avenues
Walk Flyover
-
Detailed
3D analysis of one of the longest and most highly curved single
span girder bridges in the world
-
Investigation
of lower lateral bracing requirements
-
Uplift
analysis for deck pour sequence
Avenues Walk Flyover is a
single-span curved girder bridge that spans the Florida East Coast
Railroad to provide access to a private mixed use development on a
restricted site south of Jacksonville. GAI Consultants used LUSAS
Bridge analysis software for detailed 3D analysis and comparison
checking of the structure, and notably to investigate lower lateral
bracing options and to provide a means of reducing uplift during a
slab pour construction sequence.
Overview
Avenues
Walk Flyover provides access to a triangular-shape mixed-use
development site bounded on two sides by Interstate 95 and the Florida
East Coast Railroad.
The
bridge alignment was essentially dictated by the grade required for
the access road to rise sufficiently within the land space available in
order to meet a specified railroad clearance. The severe curvature and
length of the resulting bridge required the development of innovative
design and construction methods to meet both geometric and economic
restraints. GAI’s eventual solution, with a span length of 218’, a
width of 79’ and a centerline radius of 300’, means that Avenues
Walk Flyover is one of the longest and most highly curved single span
girder bridge structures in the world. |
|
To achieve the combination
of span and curvature for this bridge required unique design elements
in order to optimize capacity and ensure stability. Varying end skews,
non-uniform girder spacings and girder depths, lower lateral girder
bracing, uplift resistant bearings, a 32 ton concrete counterweight,
and a transversely staged deck pour would all end up being
incorporated into the final design.
|
Initial and
re-designed bridge alignments and final single deck solution |
Bridge development
Concept designs looked at
a single-span and a three-span option, with the lower cost single-span
option being preferred by the developer. For this, separate 37’
wide, single-span eastbound and westbound structures were initially
proposed but the potential for uplift on these separate, narrow, and
highly curved structures resulted in one single 73’ wide structure
of greater stability being chosen. Further investigations into
different skew arrangements and relative stability/uplift issues for
this wider structure resulted in a final solution which used parallel
end supports, one radial with some potential for uplift, and the other
skewed to the roadway at about 45 degrees. To support the deck, eight
centrally placed, equally spaced girders were proposed, but from
analysis carried out it was found that, because of the severe
curvature of the deck, the two girders on the outside edge were
carrying four to five times more moment than the innermost girder.
This caused GAI to move the set of girders more toward the outside of
the curve, reducing the deck overhang. This gave a beneficial 10
percent reduction in load distribution for the most heavily loaded
girder. Girder spacing was also adjusted. Spacing for the two outer,
120” deep girders was decreased from a fixed 9’-5” to 8’-0”,
and the five inner, 104” deep, girder spacings were increased to 10’-0”.
The 300’ centerline radius on the bridge required a 4%
superelevation, making the outside curb line almost 34 inches higher
than the inside curb line. Because of this, the outside girders, which
are only 16” deeper than the inside girders, do not control the
under-clearance, so by using shallower girders for the inner six
locations, ten valuable inches of overall bridge height were saved.
Analysis and design
In order to verify the
bridge’s behaviour during both erection and in-service loading both
grid and finite element analysis software was used. 2D grid analysis was employed essentially as
a ‘framework’ tool
for overall girder design, flange
plate optimization, diaphragm design, and bearing design. 3D finite
element analysis
with LUSAS Bridge was used for detailed design to make sure that 3D
effects were being accounted for in the individual bridge elements -
something not possible with a grid analysis. Using LUSAS, dead load
effects were assessed and final construction deflections were derived. Live loading was analysed for each vehicle lane with
combinations and envelopes producing worst-case values. LUSAS was also
used investigate bearing stiffnesses, lower lateral bracing loading,
and to assess potential uplift from transverse deck pour sequences. A
final analysis of the complete proposed design was carried out by a
third party to verify the results obtained.
|
LUSAS 3D modelling
of Avenues Walk Flyover showing vehicle loading to inner lane |
Lower
lateral bracing
Using LUSAS Bridge, GAI
investigated lower lateral bracing options to carry wind and lateral
stresses in the plane of the girder bottom flange. Three arrangements
were examined; lateral bracing in both exterior bays and one internal
bay, lateral bracing in the exterior bays only, and lateral bracing in
the outside girder bay only. Based on some preliminary analysis, it
was determined that final condition lateral deflections and stresses
were not large enough in the innermost girders to warrant the cost of
installing lateral bracing in that bay. In the erection condition,
however, the use of lower lateral bracing would have had an impact on
the magnitude of lateral deflection if the interior girders were
erected first. Since the planned construction sequence was to erect
the outside girder pair first, the potential advantage of lateral
bracing would not, in fact, be realized. The final design included a
single bay of lower lateral bracing, placed between the two outermost
girders. |
|
Deck pour sequence
analysis
The steel frame was
erected on two falsework towers. However, prior to the deck placement,
the towers were removed. As a result, uplift, calculated to be caused
by pouring the deck, had to be overcome. With the entire steel frame
in place to resist the effects of overturning, a concrete
counterweight weighing 32 tons was placed adjacent to the inside edge
girder at the radial abutment to reduce any uplift forces.
Additionally the deck was placed in two transverse deck sections with
the deck over the four innermost girder lines placed first. After the
deck cured, the remaining section of the deck was placed, with the
first pour acting as a counterweight. The bridge was constructed using
uplift resistant bearings and uplift resistant foundations at the
inside edge of the radial abutment so that there was adequate capacity
for the entire uplift including live load effects shown in the
worst-case analysis model.
From analyses, mid-span
dead load deflections were calculated and compared for each girder.
After the removal of the falsework towers the calculated deflection
for the outermost girder varied from 10.8 inches in the LUSAS 3D
finite element model to
13.4 inches in the 2D grid analysis model, a variation of about 25 percent. This
difference would be largely due to the limitations of grid analysis to
include lateral bracing effects. The models showed good agreement
regarding the end reactions and the uplift potential at the radial
abutment. For the maximum downward reaction case at the outermost
girder the models all agreed within 2 percent.
Samuel N. Spear, engineer
at GAI Consultants said: “LUSAS proved to be a valuable tool for the
project. We especially enjoyed the ability to model the various stages
of construction and in-service loading. He was also complimentary of
the LUSAS support staff: “When we required modelling assistance the
LUSAS support staff were helpful in answering our questions when the
need arose”.
Avenues Walk Flyover
Project Stakeholders
-
Owner: City of
Jacksonville, Florida
-
Engineer: GAI
Consultants, Inc.
-
Contractor: Hal
Jones, Inc.
-
Railroad:
Florida East Coast RR
-
Developer: KIMCO Developers,
Inc.
“LUSAS proved to be a
valuable tool for the project. We especially
enjoyed the ability to model the various stages of construction and
in-service loading... and when we required modelling assistance the
LUSAS support staff were helpful in answering our questions when the
need arose”
Samuel N. Spear, GAI
Consultants
Share this
article
Find out more
Other LUSAS Bridge case studies:
|
|
Software Information
|