Bridge analysis, design + assessment

Case Study

Share this article 

 

Chelsea Street Bridge

  • Construction engineering analyses for a vertical lift bridge

  • Staged construction analysis for concrete counterweight pours

  • Determination of stresses, displacements and jack reactions during the launching of a massive steel truss

Chelsea Street Bridge during lifting
(Image courtesy of J.F. White Contracting Co.)

As part of its appointment to provide pre-bid and construction engineering services to J.F. White Contracting Co. for the Chelsea Street Bridge Replacement Project, Finley Engineering Group, Inc. (FINLEY) developed an erection scheme for a new single span vertical lift bridge that allowed a massive steel truss to be erected on-site and launched into its final position. FINLEY used LUSAS Bridge analysis software to assist with this task and also to analyse the stresses on temporary steel bracing as a result of pouring of concrete into the steel plated counterweights.

Overview

Old Chelsea Street bascule bridgeThe Chelsea Street Bridge project, funded by the Massachussetts Department of Transportation, involved the replacement of a 75-year old single leaf bascule bridge (shown right) that spanned across the Chelsea Creek in Boston and Chelsea with a new vertical lifting bridge. The old bridge had an overall length of 446 ft (136m) and was a six span structure with a mainspan consisting of a 140 ft (43m) heel trunnion Strauss bascule with 66 ft (20m) and 42.5 ft (13m) spans on the east side and three, 66 ft (20m) spans on the west side. The bascule span itself spanned a 96 ft (30m) wide channel that restricted shipping and was a notable hazard to navigation. 

The new replacement structure, designed by HNTB Corporation, consists of a massive constant-height warren-type steel truss that spans 450 ft (137m) between two, 216 ft (65m) high towers, and when raised gives 175 ft (53m) of vertical clearance for shipping. It matches the footprint of the previous bridge and its approach structures and provides for four lanes of traffic (two in each direction) along with two pedestrian sidewalks. A lack of clearance for larger vessels meant that it would have been difficult to float the truss in on barges as is commonly done for bridges of this type. FINLEY's solution was to launch a fully assembled truss 140 ft (43m) out across the navigation channel using launching girders supported on the existing bridge piers.

Towers and counterweights

The lower halves of each steel tower were assembled member by member up to mid-height. Then, preassembled 34m long, 200 tonne upper leg sections were lifted into place and fixed connections made, before topping each tower with 23m x 7.6m machine rooms that house the lifting machinery. Tower plumbness tolerances demanded verticality along the project baseline of within 2.5cm over the 65 metre height and within 1.3cm orthogonally to the project baseline. Adjustments were made to the base of each tower with reference to a network of survey stations to achieve this.

Chelsea Street Bridge : Lifting of counterweight

Chelsea Street Bridge : Lifting of counterweight

Counterweight lifting

Counterweight lifting

The 770 tonne counterweights are used on the bridge to assist the lifting motors and reduce the deadweight. These counterweights are essentially steel plated containers filled with a high density concrete that is poured in stages to prescribed depths. During the concrete pours, temporary bracing of the counterweight top flange is required to control the stresses induced in the steel container. After casting, strand jacks are used to raise the counterweights to sit underside the control room at the top of each tower. 

Counterweight analysis

A staged analysis of the concrete pours for the counterweights was required to check the effects on the steel bracing. Using LUSAS, a finite element model of the counterweight was developed using shell elements to model the outer and inner steel plates and thick beam elements to represent the lateral bracing members. The concrete pours were modelled individually as hydrostatic loads, with lifts of 5ft, 5ft and 4ft (1.5m, 1.5m 1.2m) to comply with FINLEY's balancing plan.


LUSAS modelling of steel / concrete counterweight


Analysis of counterweight concrete pours

Truss launching

Truss assembly yard The massive 1200 tonne truss/deck system is composed of built-up steel members connected to each other by gusset plates. On-site the component parts of the truss were assembled in a yard adjacent to the bridge to create two truss units. Each was then side-launched into position, joined together, and then jacked progressively along the launching girders until the truss system was ultimately fully-cantilevered out across the navigation channel prior to touching down on the opposite side. Project specifications dictated that the main river channel couldn't be closed for more than 60 hours. So, once the truss breached the channel clearance, the truss had to be launched, installed, and lifted to its maximum open position within the allotted closure period. 

For the launch of the truss, FINLEY designed the specialized launching equipment, launching girders, temporary supports and launching geometry. The existing bridge piers had been recently retrofitted and a field inspection/condition survey and subsequent evaluation for launching loads confirmed they had sufficient capacity to be used for the launch. 

Truss/deck unit for Chelsea Street Bridge (Image: Flickr MASSDOT Photostream. Permission of use sought on 11/06/12)

First truss unit assembled in readiness for launching

Truss launching analysis

The main purpose of the launching analysis with LUSAS was to ensure that member stresses and truss displacements during launching of the truss remained within tolerable limits. All truss members were modelled using thick beam elements placed at member centroids. Section properties for each member were calculated using the section property generator within LUSAS. All loads and stages in the launching process were modelled and analysed in LUSAS with envelopes of worst effects being obtained. The fully-cantilevered condition was the most demanding, causing the highest jack reactions and forces/stresses in the members. Jack Pecora, Project Manager at J.F. White Contracting Co. said: "FINLEY’s use of LUSAS provided us with updated support point reactions (bogey reactions) once the final launch load and sequence was engineered. This was most critical through the launch phases as the truss model was used to confirm observed reactions from the field."


Fully cantilevered position of truss during launching

 

LUSAS model of truss for fully cantilevered launch position

 

Axial forces in truss members at fully cantilevered launch position.

 

Chelsea Street Bridge : Launching of truss over existing channel

Launching of truss over navigation channel

The truss was launched across the shipping channel in mid-November 2011. Following final fitting-out work of the deck system and removal of all existing temporary works and mid-channel piers, the shipping channel was dredged and widened to allow the passage of larger vessels. After additional unforeseen work that required the removal of an abandoned sewer line beneath the channel, the $125 million bridge was officially opened on 14 May 2012.

Jerry M Pfuntner P.E. at FINLEY said: "The use of LUSAS helped us prove our erection design. Early communication between the client Massachusetts DOT, the Contractor J.F. White and FINLEY created a construction solution that took the Contractor’s strengths into account and maximized the use of existing support structures to create a reliable and efficient erection plan."

 

Chelsea Street Bridge (Image courtesy of J.F. White Contracting Co.)

Chelsea Street Bridge fully raised
(Image courtesy of J.F. White Contracting Co.)


The use of LUSAS helped us prove our erection design. Early communication between the client, Massachusetts DOT, the Contractor, J. F. White, and FINLEY created a design that took the Contractor’s strengths into account and maximized the use of existing support structures to create a reliable and efficient erection plan".

Jerry M Pfuntner, P.E., Finley Engineering Group, Inc.


Share this article 

 


Find out more

LUSAS Bridge

Software products

Software selection

 


 

Other LUSAS Bridge case studies:

Software Information

  Bridge / Bridge plus
green_arrow.gif (94 bytes) Software overview
green_arrow.gif (94 bytes) Modelling in general
green_arrow.gif (94 bytes) Advanced elements, materials and solvers
green_arrow.gif (94 bytes) Load types and combinations
green_arrow.gif (94 bytes) Staged construction modelling
green_arrow.gif (94 bytes) Geotechnical / Soil-structure modelling
green_arrow.gif (94 bytes) Analysis and design
green_arrow.gif (94 bytes) Design code facilities
green_arrow.gif (94 bytes) Viewing results
green_arrow.gif (94 bytes) Software customisation

  Bridge LT
green_arrow.gif (94 bytes) Software overview

  Choosing software
green_arrow.gif (94 bytes) Software products
green_arrow.gif (94 bytes) LUSAS Bridge LT
green_arrow.gif (94 bytes) LUSAS Bridge
green_arrow.gif (94 bytes) LUSAS Bridge Plus
green_arrow.gif (94 bytes) Software selection
green_arrow.gif (94 bytes) Software options

green_arrow.gif (94 bytes) Videos
 
green_arrow.gif (94 bytes) Case studies

  Application areas
green_arrow.gif (94 bytes) Footbridge design
green_arrow.gif (94 bytes) Movable structures
green_arrow.gif (94 bytes) Rail solutions
green_arrow.gif (94 bytes) Arch bridges
green_arrow.gif (94 bytes) Major crossings
green_arrow.gif (94 bytes) Soil-Structure Interaction Modelling

  Additional information
green_arrow.gif (94 bytes) Linear and nonlinear buckling analysis
green_arrow.gif (94 bytes) Curved girder analysis
green_arrow.gif (94 bytes) Integral or jointless bridges
green_arrow.gif (94 bytes) Post-tensioning
green_arrow.gif (94 bytes) Concrete modelling
green_arrow.gif (94 bytes) Interactive Modal Dynamics
green_arrow.gif (94 bytes) LUSAS Programmable Interface (LPI)

  General information
green_arrow.gif (94 bytes) Hardware specification
green_arrow.gif (94 bytes) Licencing and Networking options
green_arrow.gif (94 bytes) Software prices
green_arrow.gif (94 bytes) Documentation
green_arrow.gif (94 bytes) Links page
 

Request information

 


innovative | flexible | trusted

LUSAS is a trademark and trading name of Finite Element Analysis Ltd. Copyright 1982 - 2022. Last modified: March 07, 2023 . Privacy policy. 
Any modelling, design and analysis capabilities described are dependent upon the LUSAS software product, version and option in use.