Case
Study
Assessment of Brick Vaulted Arches at Glasgow
Central Station
- Linear elastic modelling of a
multi-span vaulted arch structure for load assessment
- Nonlinear analysis of a single
vaulted arch using a multi-crack concrete material model
- Adequacy for RA8 loading
confirmed
At Glasgow Central Station, Network Rail
wanted to increase the station's capacity by replacing a short stay car park
at platform level with two additional tracks and platforms. The Platforms 12 & 13 Design
& Build Contract required support to
be provided to two, 340m lengths of new permanent way, 90m of which was
supported by brick vaulted arch geometries constructed
in the early 1900’s and not previously exposed to rail loading. URS worked as the designer for Balfour Beatty and used LUSAS
Bridge analysis software to assist with its assessment of the vaulted
arch structures and confirmed their adequacy for the required RA8
assessment loading.
Overview
Glasgow Central Station was constructed at the beginning of the 20th century
and has Category A listed status. It is the Northern Terminus of the
West Coast Main Line and handles 34 million passengers a year,
making it one of the busiest stations in the UK outside London. All
tracks at the station are between 7 and 8 metres above existing ground level so
support for the new tracks needed to be provided by existing steel
structures, existing masonry vaulted arches and some new build work.
Geotechnically the site is complicated. Due to proximity of the
River Clyde, a varied mix of alluvial clays, sands and silts are
present, in varying depths and layering, and with significant differences over the length of the site
in the direction of the river. The theoretical soil strength was low, suggesting
that the allowable bearing pressures were being exceeded by the existing permanent
load, but there was very little observable cracking or other signs of distress in
the arch structures to support this. The arches appeared
to be in generally good condition
considering the masonry had been constructed 100 years ago. It was
concluded that the slow construction method had allowed settlements to occur during construction
that had been continually corrected as the works progressed leaving minimal post-construction settlement or cracking.
|
|
Before: Short stay
car park
between platforms |
After:
New permanent way installed |
Installation of the two new
tracks required the removal of the short stay car park slab and support walls, and
replacement with the slab-track and permanent way. This would result in a
slight reduction in the permanent loads on the substructure but live loads
would increase from light road vehicle use to RA8 assessment loading
for goods trains. As a result the total load would increase by up to 20%.
New permanent works
proposed as part of the platform design and build contract would
enhance the foundation bearing capacities by bridging the gap between the
existing piers. In addition, a bridging slab would prop the existing
pier foundations and also help to prevent slip planes forming between
the sets of foundations by providing a single, long foundation
instead.
Modelling
with LUSAS
The assessment method
adopted was a progressive one. It started with the creation in LUSAS
of a 3D
linear elastic global solid model of an arrangement of
substructures to get a feel
for the stresses involved and also to assess the bearing pressures
under the foundations and provide input with regard to spring
stiffnesses for use in a later nonlinear analysis. The region of substructure
chosen for modelling (shown below) was considered to have the least
restraint. The void seen in the centre of the model was to be filled
with new reinforced concrete works but these would not be supporting
the existing structures.
|
Geometry
model for an initial linear elastic assessment of a selected
region of substructure |
Nonlinear
analysis
A solid nonlinear model of
an individual vaulted arch was created for detailed analysis using the
LUSAS multi-crack concrete material
model. Initially, brick properties were
obtained from CIRIA C656. Dr Danny Boothman, project engineer at URS
said, "Although we were looking at a brick arch it was felt that
because of the number of bricks in the arches it was approximating to
a homogeneous material and essentially the mechanism for load transfer
was very similar to low strength concrete with minimal tensile strength and thrust generating
through the arches". Haunching and back-fill
was modelled using a Mohr-Coulomb material model with a low tensile
strength and a high angle of friction. Boundary conditions were modelled as sprung,
free and fixed, although the material models employed prevented a significant build up of tension.
|
|
Geometry model
for a nonlinear analysis of a single vaulted arch |
Calculated
crack
patterns under existing permanent loading |
A significant amount of
time was spent on parametric sensitivity studies to identify critical input parameters
and provide upper and lower bound
values for the LUSAS concrete material model. Danny Boothman explains,
"Many parameters needed to be defined for the multi-crack concrete
model and we found that some were more sensitive than others -
particularly the uniaxial tensile strength and the fracture energy per
unit area. The input parameters for
the LUSAS models were calibrated against the observed effects of the
dead loads on the arches. Additional loading to represent the RA8 rail
loading was then applied and the resulting cracking and deflections
were used to demonstrate the adequacy of the structures for RA8
loading. As anticipated, the results were particularly sensitive to the support stiffnesses at springing level, as well as some material parameters including tensile strength - both of which are difficult to predict reliable values for."
|
|
Stresses
from RA8 loading |
Stresses
from RA8 loading (underside of arch) |
Summary
Overall this was a
challenging assessment, completed using the multi-crack concrete model
in LUSAS, and calibrated against existing conditions. Because a relatively
novel analysis was used to undertake the assessment using the
pre-construction condition as a calibration basis for the modelling it
would have been beneficial to have had load test data for higher
loadings to corroborate the results, but this was not possible.
However, a number of areas of conservatism in
the analyses carried out were felt to be sufficient to justify the
approach taken:
-
The backing layers to
the arch were actually found to be mass concrete and therefore vertically self supporting.
-
The calibration of the
FE model against observations indicated that the model was
conservative, predicting greater cracking under existing loads
than was seen on site. This conservatism was acceptable since the
purpose of the analysis was to demonstrate adequacy under RA8
loading rather than determine a maximum load capacity.
-
The load spreading benefit of
the reinforced concrete slab track was ignored.
-
A third party check
using discrete element modelling
corroborated the results and reached similar conclusions.
-
Platform use is limited to very low speed passenger trains (significantly below RA8)
because Glasgow Central is a terminus station.
-
Monitoring
of the vaulted arches under rail loading was also undertaken to
further validate the findings of the assessment.
Danny Boothman sums the
project up as follows, "Although there was new-build work on
this project which might have grabbed the headlines from a
photographer's point of view, the real crux of this project from a
design/assessment perspective was
being able to justify the new railway tracks over 90m of old vaulted
arches."
"Although there
was new-build design work on this project, which might have grabbed the
headlines from a photographer's point of view, the real crux of this
project from a design/assessment perspective was being able to justify the new railway tracks over 90m of
old vaulted arches."
Dr. Danny Boothman,
Project Engineer, URS.
Find out more
Other LUSAS Bridge case
studies:
|