Case
Study
Share this
article
West Gate Bridge Upgrade
- Strengthening
of a major steel box girder bridge for extra traffic lanes
- Global
and local finite element modelling
West
Gate Bridge crosses the mouth of the Yarra River in Melbourne,
Australia. Its 2.6km overall length comprises two concrete box
girder high level approach viaducts either side of an 850m long,
5-span cable stayed steel box girder bridge with a 336m main span.
The bridge forms a vital link in Melbourne’s main East – West
transport corridor, the whole of which has undergone a substantial
upgrade to provide increased capacity. Flint & Neill
used
LUSAS Bridge analysis software to undertake global and local finite
element modelling to analyse methods of strengthening the
steel box girder for increased vehicle loading, by cantilever
propping, internal stiffening, and post-tensioning; and for the management
of construction loads.
History
Flint
& Neill's involvement with West Gate Bridge goes back to the 70s
when, following a tragic collapse during construction, it was appointed by
Redpath Dorman Long to develop a re-erection scheme for the bridge.
After a major re-design and a successful construction the bridge
eventually opened in 1978. The bridge was built with 4 lanes of
traffic in each direction, and prior to this upgrade was carrying 160,000
vehicles per day and in need of extra capacity. It was required to
upgrade the bridge to 5 lanes, as part of a contract between the
State of Victoria, Transurban Infrastructure Management Ltd and
Citylink Melbourne Ltd, to tie in with the M1 upgrade works. The
bridge upgrade works were undertaken by an Alliance in which Flint
& Neill had the major responsibility for the assessment and
strengthening design for the steel bridge; advice on inspection,
operation and maintenance; developing designs for early works
improved access; and for producing a current set of electronic
as-built drawings from historical documents and original drawings.
Structural
overview
The deck on West Gate Bridge is a
continuous steel box girder of 4m in depth with plate thicknesses
varying from 10 to 25mm. The overall width including the cantilevers
is 37m. Inside, the box girder is divided into three cells by four
longitudinal webs and has plated diaphragms every 16m. All plates
are heavily stiffened with the majority of stiffeners being the old
bulb flat type. The deck is cable supported along its centreline by
two sets of cables which pass over saddles at the steel box tower
heads and splay out at deck level into cable anchorages within the
steel deck box.
|
|
Lane arrangement
prior to upgrade |
View inside box
girder |
|
|
Strengthening
scheme
The
strengthening solution adopted was to prop the existing
cantilevers and turn the existing hard shoulder into a running
lane. Other options were considered that required widening the
carriageway slightly but studies had shown that it was safe to
reduce lane widths (to 3.2m in this case) over short distances
without adversely affecting road safety, and this proved to be
the least expensive option. As well as propping of the
cantilevers a lot of internal strengthening to the deck and
towers was required to cope with the additional traffic
loading. |
|
Modelling with
LUSAS
Very early in
the project Flint & Neill decided to create a shell element
model of the whole cable stayed bridge structure in LUSAS. Peter
Robinson, one of the projects engineers involved said,
"Ordinary desktop computers are now capable of running a shell
model of the entire bridge, which is great for modelling the
distortional and shear lag stresses around the cable anchorages in
wide boxes such as West Gate." A rigidity matrix was
defined to model the orthotropic effect of the stiffened plates.
Linear elastic analysis was used to allow load combinations to be
assessed.
|
|
LUSAS
model of West Gate Bridge, showing the permanent load
deflection and cable creep |
Live
load modelling |
Loadcases considered
For
the permanent loadcase a survey carried out in 2007 showed that the
central span of the bridge had deflected by around 330mm over the
years due to the creep and sagging of the cables. Although the
stretching of the cables didn't change the tensions in them very
much it did add considerably to the stresses in the deck when
sagging at mid-span and when hogging at the towers. In the LUSAS
assessment model the initial stress in the cable stays was adjusted
to represent creep and the deck profile was matched to that of the
2007 survey. An as-built profile was also modelled to allow
re-tensioning of the cables in the future.
For
live loading, the traffic load definition was specific to West Gate
Bridge and was derived from weigh-in-motion data where the weights
of vehicles crossing the bridge were recorded and analysed to derive
the extreme loading. Traffic loads were generated using Autoloader
traffic load optimisation software which required the creation of
over 700 traffic loadcases to assess maximum stress along the box
girder, and in the bearings and cables. For wind loading static
loadcases were derived from the gust buffeting response of a spine
model.
Because
of the history of the bridge the handling of the construction loads
was a particularly sensitive issue, made all the more difficult
because the bridge was overstressed under the existing eight lane
traffic loading. For reasons of safety, it was required to position
concrete barriers along the bridge during the upgrade works which
added considerable weight. It was decided to limit the loads during
construction to the maximum theoretical 8 lane loading before the
strengthening had started. This was achieved by modelling the full
sequence of gantry movements and resulted in night time lane
restrictions for a long period and restrictions on the allowable
movements of gantries.
|
|
Modelling
of construction loading |
Detailed modelling
Because Flint & Neill chose to
create a shell element model of the whole bridge in LUSAS it was
straightforward to refine the mesh in certain areas of interest to
investigate localised effects. This had other benefits too as Peter
Robinson explains: "Having a single global shell model meant
that there was no need to worry about specifying boundary conditions
or applying suitable loading as would be required for looking at
regions of the structure using separate localised models, and this
was a big plus." He continues: "The model also showed how
the distribution of loads in the webs and diaphragms of the
anchorages took place. It's worth pointing out that for the
assessment carrying out the analysis with LUSAS was only half the
story. We also had the task of checking against all the element
(member) capacities which, for stiffened structures such as this box girder,
can be very complex."
|
|
Detailed
modelling around cable anchorage |
Stresses
in anchorage plates |
Codified checks were carried out to
BD56 and to IDWR (Interim Design and Assessment Rules). These rules
were drawn up in the 1970s following the collapse of bridges such as
Milford Haven and West Gate Bridge and were felt by Flint &
Neill to be the most appropriate assessment tool for the upgrade
project. Localised modelling and nonlinear analysis with LUSAS was
used to improve torsional buckling capacity of the bulb-flats beyond
codified values resulting in a reduction of the strengthening
required being obtained.
|
|
View
of bulb flat stiffened plates showing different types of
strengthening |
Analysis
of bulb flat stiffened section of box |
Strengthening required
At the start of the strengthening
project a lot of work was done to improve the access to the box
girder. This saw the enlargement of the central reserve manholes,
end pier soffit openings, internal walkways and of the diaphragm and
inner web openings where possible. The outside of the bridge has seen
the addition of 528 cantilever props, which were installed over a 12
month period using gantries slung beneath the cantilevers. Substantial strengthening was carried
out inside the box to the bottom flange and webs. This took the form
of extra stiffening to the existing stiffeners and the addition of
some new stiffeners. The box walls and diaphragm around the pier
bearings required heavy strengthening in an already congested area. Prestressing strands were also used
inside the box girder to overcome tension overstress in the bottom
flange plate and overstress at the splice plates. The prestressing
extends over a 60m length of flange, passing through holes drilled
in the flange stiffeners, with plated anchorages at each end. Additional stiffening of the towers
was also required requiring the fitting of new plates in the region
where the tower penetrates the deck level and for these close
tolerance bolts were used to avoid weakening the existing structure.
|
|
Installation of
cantilever props |
Prestressing of
bottom flange |
|
|
On completion of the upgrade work the additional traffic lanes were
opened for use in June 2011.
"Having
a single global shell model meant that there was no need to worry
about specifying boundary conditions or applying suitable loading as
would be required for looking at regions of the structure using
separate localised models, and this was a big plus."
Peter Robinson,
Project Engineer, Flint & Neill
A presentation titled 'West Gate
Bridge Upgrade' was given
by Peter Robinson of Flint & Neill at the 2012 International
Bridge Analysis Seminar "Assessment
and Rehabilitation of Bridges" held in London on 7th March
2012. |
|
|
Lane arrangement
after upgrade |
Awards
Share this
article
Find out more
Other LUSAS Bridge case studies:
|