Share this
article
Case
Study
The Kids' Bridge
-
Detailed structural analysis
of a winding steel through girder bridge with nonlinear
FE analysis of steel connections
-
Staged construction modelling
and optimisation of member sizes
-
Detailed assessment of
pedestrian induced vibrations to validate the design
PCH
Kids' Bridge - Perth, Western Australia, built by Main Roads Western
Australia.
AECOM
was engaged by Main Roads Western Australia to undertake the detailed
design of a curved and colourful bridge connecting Perth Children's
Hospital to an adjacent park. The bridge had to be constructable with
the modest available budget and address the concerns of the numerous
stakeholders. AECOM chose to use LUSAS Bridge analysis software to
assist it with its design in order to overcome the challenges imposed.
Overview
The visually stunning Kids’ Bridge provides safe
and direct access from the Perth Children’s Hospital and QEII
Medical Centre Campus to Kings Park, the most visited destination in
Western Australia. A highly constrained site resulted in the use of a
through girder design comprising fabricated steel box girders, which
provided an efficient solution to accommodate the serpentine
alignment. Detailed structural analysis with LUSAS, along with a
detailed assessment of human-induced vibrations allowed the design
team to reduce the number of piers along the bridge's length. The
result is an iconic design offering users an experience filled with
vibrant colours, sweeping curves, long open spans, inbuilt speakers
amplifying nature sounds, programmable feature lighting, and a treetop
walk.
Bridge description
The total bridge length of approximately 217m
comprises 170m of elevated structure, with approach ramps of 30m and
17m at each end. The elevated structure comprises six continuous
spans. The two main spans over Winthrop Avenue are approximately 38 m
long, with the remaining approach spans having a maximum span of
approximately 29m. The alignment comprises eight distinct horizontal
curves in addition to a vertical curve over Winthrop Avenue. The
superstructure is a through girder design comprising two 1200mm deep
by 400mm wide fabricated steel box girders. The box girders are braced
by 250mm deep RHS cross beams and a stiffened steel plate. A 125mm
thick concrete deck acts compositely with the stiffened steel plate
and box girders. The deck is supported on proprietary pot bearings. A
through girder design was selected to reduce the superstructure depth
extending below the finished surface, which reduced the overall bridge
length and the amount of clearing and disturbance within Kings Park.
The piers comprise inverted U-frames constructed
from fabricated steel box sections. The column box sections taper from
300mm at the base to 400mm at the top, with the top horizontal member
having a constant width. The piers are supported on concrete spread
footings, except for the central pier which is supported on piles. The
abutments comprise concrete L-shaped retaining walls. The box shape on
the bridge continues along the approach ramp retaining walls to
provide continuity of form for the full length of the bridge and
approaches. The walls are inset from the box section to accentuate
this feature.
|
Typical cross-section |
Modelling
with LUSAS
AECOM used LUSAS Bridge to model the structure and
undertake the required dynamic and buckling analyses. Beam elements
represented the asymmetric box girders, cross girders, and pier
columns, with shell elements used to model the concrete deck,
stiffened deck plate and spread footings. Offsets were used to ensure
the correct eccentricity of the respective elements. Springs modelled
the soil stiffness.
|
LUSAS model |
Staged construction modelling
An accurate construction stage analysis was required
since the girder articulation and stiffness varied throughout the
construction stages. The continuous girders were initially erected as
simply supported segments on temporary props. Girders segments were
then spliced, and the props were subsequently removed. The concrete
deck, which acts composite with the girders, was then cast. The
analysis also included time-dependent creep and shrinkage of the
concrete deck slab.
Optimised workflow and member
sizes
Locating piers was challenging due to the serpentine
alignment, and the highly constrained site. The design workflow
enabled various span arrangements to be compared quickly. This allowed
the design team to balance spans and reduce the number of supports.
The serpentine alignment, combined with the asymmetric longitudinal
girders, resulted in the longitudinal girders being subject to design
actions about each axis, and the cross girders being subject to
significant induced forces. The workflow enabled numerous permutations
of the main girder size, and cross girder sizes and locations to be
analysed to improve the structural behaviour and reduce material
quantities.
Pedestrian loading assessment
The assessment of human induces vibrations was
critical due to the serpentine alignment with its tight curves and
large cantilevers. The acceptance criteria and analysis methodology
contained in "Design of Lightweight Footbridges for Human Induced
Vibrations, JRC Scientific and technical reports (2009)" was used
in addition to AS 5100.2 requirements. The JRC Report is a result of
two European research projects into human induced vibrations on
footbridges to harmonise design rules and develop the Eurocodes. The
JRC Report links load scenarios (pedestrian densities) that are
anticipated during the life of the bridge to a comfort class
(acceleration range) based on the expected frequency of the load
scenario. Three load scenarios were devised for this bridge which
covered daily commuter/recreational traffic through to crowd loading
on opening day. Horizontal modes of vibration less than 1.2 Hz were
eliminated by pinning the bridge at each support. The flexibility of
the steel piers resulted in small locked-in forces but was sufficient
to push the first lateral model of vibration to 2.5 Hz.
|
Typical dynamic assessment |
Several vertical modes of vibration less than 5 Hz
were found, with critical modes at approximately 1.7 Hz and 2.1 Hz.
Peak accelerations for each mode and each design case were determined
from a dynamic analysis. The calculated peak accelerations were found
to be within the selected comfort
criteria. The bridge has been subject to various
load scenarios, including crowd loading on opening day, with no
complaints about unpleasant vibrations, validating the modelling and
assumptions made in the design.
Finite element
analysis
Separate nonlinear models were created to analyse the
stiffened steel connections and supplement hand calculations. This was
particularly important given the concentrated forces imposed on the
hollow sections at cross girder connections, bearing locations, and
the large web openings to house the speakers.
|
|
Deck
fabrication |
Deck
assembly |
|
|
|
|
Welded
splice |
Deck cantilever |
"The
design of the Kids’ Bridge had a unique set of challenges specific
to the site. Detailed analysis using LUSAS and collaboration with
fabricators enabled the design team to challenge the status quo and
design an economic and visually stunning structure."
Nicholas
Keage, Principal Engineer and Michael
Kakulas, Associate Director, AECOM Awards
- 2022 Western Australia Engineers Australia
Excellence Award Winner.
- Property Council of Western Australia Best
Community Infrastructure Award Winner.
- Western Australia Architecture Awards
Commendation.
- Dulux Colour Awards Commendation.
Share this
article
Find out more
Other LUSAS Bridge case
studies:
|