Case Study
Share this
article
Advancing Segmental Bridge
Technology
-
Analysis and
optimization of post-tensioned precast concrete bridge segments
-
Precasting
details simplified
-
Faster
erection and improved durability
Finley
Engineering Group, Inc. (FEG) of Florida is providing
final design and construction engineering services for six
segmental bridges on Israel’s Road 431 project - the first in
Israeli bridge construction history to use external tendons. FEG
used LUSAS Bridge to analyse and optimize the pier and deviator
segment diaphragms for the imposed loadings whilst keeping the
segment weight within the 65 tonne lifting capacity of the
contractor’s equipment. As a result of FEG’s design the owner
and contractor were provided with major benefits from simplified
precasting details, thinner sections, rapid erection procedures
and improved long-term durability.
Overview
Israel has constructed more than 25
segmental bridge structures in the last 20 years. But despite the
country’s considerable experience with segmental bridges, the six
FEG-designed bridges for one of the interchanges on the 21km long,
Design-Build-Operate-Transfer venture will be the first in Israeli
bridge construction history to use external tendons. These 12.5m wide
bridges have span lengths ranging from 30m to 66m and consist of 501
precast segments with a total deck area of more than 18,000 square
metres.
Road
431 Project, Israel
Road 431 is a lateral access
road to the Cross Israel Highway
(Highway 6) and constitutes the southern traffic
artery of the ring road surrounding the Greater Tel Aviv
Metropolitan Area (Gush Dan), consisting of Ayalon Highway in
the West, Highway 6 in the East and Road 531 in the North. The
road connects between Rishon-Letzion in the west and Modi’in
in the East. |
|
|
|
Design and Construction
Challenges
The contractor, Danya Cebus, Ltd., was
challenged with a tight construction schedule to meet concession
agreement requirements and project financing goals. As a result, FEG
proposed the use of external tendons to allow for simplified
precasting of the segments, reduction in segment cross-sectional area
and foundation loads, fewer tendon stressing operations and a reduced
design schedule. FEG worked with the contractor during a streamlined
final design process that began in February 2006 and resulted in the
casting of the first segment in July of the same year. The project
involves many challenges commonly seen in today’s construction
environment, including a rapid construction schedule and budgetary
restrictions.
The contractor also required details
that enhanced the long-term durability of the structure because they
must own and maintain these bridges in satisfactory condition for 30
years before transferring ownership to the government. Due to the span
lengths and size of the segments, FEG’s technical director, Jacques
Combault, proposed a combination of internal and external tendons to
maximize the efficiency of these precast box girder bridges. Internal
tendons are used in the top slab in support of the crane-based
balanced cantilever construction, and external tendons are utilized
for all continuity post-tensioning. This system was developed with the
contractor for more consistent segment precasting configurations,
rapid installation of continuity tendons and fewer tendon stressing
operations.
|
|
Schematic of
end, deviator and pier segments showing the external tendon
arrangement |
Schematic of a
deviator and a pier segment showing tendon arrangement |
The design process included a technical
review by Israeli General Consultant engineers to confirm that the
external tendon system adequately met the project requirements. To
assist the Israeli engineers in evaluating external tendon
post-tensioning systems, FEG produced a technical white paper that
included details of previous projects, excerpts from technical
articles, and a list of benefits that the external tendons bring to
the project. It also included FEG’s analysis of tendon loss
scenarios to meet strict bridge security requirements and design
methodology for service and ultimate limit state design with external
tendons.
External tendon
benefits
The use of external tendons also
provided technical advantages in the bridge design, such as increased
ductility for flexural moment resistance and a significant reduction
in principle tensile stresses in the box girder webs. These benefits
allowed for longer, constant-depth span lengths for the bridges while
still meeting the interchange design requirements. "The large
anchorage zones required for external tendons presented a challenge in
keeping the pier segment weight within the 65 tonne lifting capacity
of the contractor’s equipment ", said Craig Finley, President
of Finley Engineering Group, "but by using LUSAS we easily
modified complex shapes and efficiently optimized the internal pier
segment dimensions".
Along with the introduction of external
tendons, FEG incorporated several other innovations on this project,
including the use of diabolos in the pier segments and deviators to
simplify the external tendon details. These post-tensioning details
allow for replacement of the external tendons should this be required
in the future. FEG also specified the use of pre-packaged grouts,
multiple levels of protection and enhanced duct systems to improve
post-tensioning system performance.
|
Deviator segment
model |
Jerry
Pfuntner, Principal Engineer at FEG said: "The segment
models created with LUSAS Bridge helped the Israeli design
reviewers to feel comfortable with the external tendon
details. The models showed the stress levels in the box girder
webs, bottom and top slabs as a result of the external
deviation forces. This helped FEG to obtain approval and
assure all parties that these details would work well under
service load conditions".
|
Typical stresses
in deviator segment model |
In summary
The use of external tendons on a
segmental bridge project is not a revolutionary concept. But, by
assessing the contractor’s needs and introducing proven segmental
bridge technologies to the Israeli construction practice, this
approach by FEG provided recognized benefits to the owner and
contractor with simplified precasting details, rapid erection
procedures and improved long-term durability. Design of the bridges on
this interchange of the Road 431 project offers another case study in
the benefits of meeting challenges by seeking solutions that go beyond
standard practice and "conventional wisdom".
"LUSAS Bridge has been a great
tool for us on this project. It allowed us to produce a design that
has major benefits for the client and contractor. We would recommend
its use to others wanting to enhance their in-house design and
analysis capabilities".
Craig Finley, President,
Finley Engineering Group Inc.
Share this
article
Find out more
Other LUSAS Bridge case studies:
|