Bridge analysis, design + assessment

Case Study

Share this article 

 

Advancing Segmental Bridge Technology 

  • Analysis and optimization of post-tensioned precast concrete bridge segments

  • Precasting details simplified

  • Faster erection and improved durability

Balanced cantilever construction on Israel's Road 431 project

Finley Engineering Group, Inc. (FEG) of Florida is providing final design and construction engineering services for six segmental bridges on Israel’s Road 431 project - the first in Israeli bridge construction history to use external tendons. FEG used LUSAS Bridge to analyse and optimize the pier and deviator segment diaphragms for the imposed loadings whilst keeping the segment weight within the 65 tonne lifting capacity of the contractor’s equipment. As a result of FEG’s design the owner and contractor were provided with major benefits from simplified precasting details, thinner sections, rapid erection procedures and improved long-term durability.

Overview

Israel has constructed more than 25 segmental bridge structures in the last 20 years. But despite the country’s considerable experience with segmental bridges, the six FEG-designed bridges for one of the interchanges on the 21km long, Design-Build-Operate-Transfer venture will be the first in Israeli bridge construction history to use external tendons. These 12.5m wide bridges have span lengths ranging from 30m to 66m and consist of 501 precast segments with a total deck area of more than 18,000 square metres.

Road 431 Project, Israel

Road 431 is a lateral access road to the Cross Israel Highway (Highway 6) and constitutes the southern traffic artery of the ring road surrounding the Greater Tel Aviv Metropolitan Area (Gush Dan), consisting of Ayalon Highway in the West, Highway 6 in the East and Road 531 in the North. The road connects between Rishon-Letzion in the west and Modi’in in the East.

Design and Construction Challenges

The contractor, Danya Cebus, Ltd., was challenged with a tight construction schedule to meet concession agreement requirements and project financing goals. As a result, FEG proposed the use of external tendons to allow for simplified precasting of the segments, reduction in segment cross-sectional area and foundation loads, fewer tendon stressing operations and a reduced design schedule. FEG worked with the contractor during a streamlined final design process that began in February 2006 and resulted in the casting of the first segment in July of the same year. The project involves many challenges commonly seen in today’s construction environment, including a rapid construction schedule and budgetary restrictions.

The contractor also required details that enhanced the long-term durability of the structure because they must own and maintain these bridges in satisfactory condition for 30 years before transferring ownership to the government. Due to the span lengths and size of the segments, FEG’s technical director, Jacques Combault, proposed a combination of internal and external tendons to maximize the efficiency of these precast box girder bridges. Internal tendons are used in the top slab in support of the crane-based balanced cantilever construction, and external tendons are utilized for all continuity post-tensioning. This system was developed with the contractor for more consistent segment precasting configurations, rapid installation of continuity tendons and fewer tendon stressing operations.

Schematic of end, deviator and pier segments showing the external tendon arrangement

Schematic of a deviator and a pier segment showing tendon arrangement

The design process included a technical review by Israeli General Consultant engineers to confirm that the external tendon system adequately met the project requirements. To assist the Israeli engineers in evaluating external tendon post-tensioning systems, FEG produced a technical white paper that included details of previous projects, excerpts from technical articles, and a list of benefits that the external tendons bring to the project. It also included FEG’s analysis of tendon loss scenarios to meet strict bridge security requirements and design methodology for service and ultimate limit state design with external tendons.

External tendon benefits

The use of external tendons also provided technical advantages in the bridge design, such as increased ductility for flexural moment resistance and a significant reduction in principle tensile stresses in the box girder webs. These benefits allowed for longer, constant-depth span lengths for the bridges while still meeting the interchange design requirements. "The large anchorage zones required for external tendons presented a challenge in keeping the pier segment weight within the 65 tonne lifting capacity of the contractor’s equipment ", said Craig Finley, President of Finley Engineering Group, "but by using LUSAS we easily modified complex shapes and efficiently optimized the internal pier segment dimensions". 

Along with the introduction of external tendons, FEG incorporated several other innovations on this project, including the use of diabolos in the pier segments and deviators to simplify the external tendon details. These post-tensioning details allow for replacement of the external tendons should this be required in the future. FEG also specified the use of pre-packaged grouts, multiple levels of protection and enhanced duct systems to improve post-tensioning system performance.

Deviator segment model

Jerry Pfuntner, Principal Engineer at FEG said: "The segment models created with LUSAS Bridge helped the Israeli design reviewers to feel comfortable with the external tendon details. The models showed the stress levels in the box girder webs, bottom and top slabs as a result of the external deviation forces. This helped FEG to obtain approval and assure all parties that these details would work well under service load conditions".

Typical stresses in deviator segment model

In summary

The use of external tendons on a segmental bridge project is not a revolutionary concept. But, by assessing the contractor’s needs and introducing proven segmental bridge technologies to the Israeli construction practice, this approach by FEG provided recognized benefits to the owner and contractor with simplified precasting details, rapid erection procedures and improved long-term durability. Design of the bridges on this interchange of the Road 431 project offers another case study in the benefits of meeting challenges by seeking solutions that go beyond standard practice and "conventional wisdom".

"LUSAS Bridge has been a great tool for us on this project. It allowed us to produce a design that has major benefits for the client and contractor. We would recommend its use to others wanting to enhance their in-house design and analysis capabilities".

Craig Finley, President, Finley Engineering Group Inc.


Share this article 

 


Find out more

LUSAS Bridge

Software products

Software selection

 


 

Other LUSAS Bridge case studies:

Software Information

  Bridge / Bridge plus
green_arrow.gif (94 bytes) Software overview
green_arrow.gif (94 bytes) Modelling in general
green_arrow.gif (94 bytes) Advanced elements, materials and solvers
green_arrow.gif (94 bytes) Load types and combinations
green_arrow.gif (94 bytes) Staged construction modelling
green_arrow.gif (94 bytes) Geotechnical / Soil-structure modelling
green_arrow.gif (94 bytes) Analysis and design
green_arrow.gif (94 bytes) Design code facilities
green_arrow.gif (94 bytes) Viewing results
green_arrow.gif (94 bytes) Software customisation

  Bridge LT
green_arrow.gif (94 bytes) Software overview

  Choosing software
green_arrow.gif (94 bytes) Software products
green_arrow.gif (94 bytes) LUSAS Bridge LT
green_arrow.gif (94 bytes) LUSAS Bridge
green_arrow.gif (94 bytes) LUSAS Bridge Plus
green_arrow.gif (94 bytes) Software selection
green_arrow.gif (94 bytes) Software options

green_arrow.gif (94 bytes) Videos
 
green_arrow.gif (94 bytes) Case studies

  Application areas
green_arrow.gif (94 bytes) Footbridge design
green_arrow.gif (94 bytes) Movable structures
green_arrow.gif (94 bytes) Rail solutions
green_arrow.gif (94 bytes) Arch bridges
green_arrow.gif (94 bytes) Major crossings
green_arrow.gif (94 bytes) Soil-Structure Interaction Modelling

  Additional information
green_arrow.gif (94 bytes) Linear and nonlinear buckling analysis
green_arrow.gif (94 bytes) Curved girder analysis
green_arrow.gif (94 bytes) Integral or jointless bridges
green_arrow.gif (94 bytes) Post-tensioning
green_arrow.gif (94 bytes) Concrete modelling
green_arrow.gif (94 bytes) Interactive Modal Dynamics
green_arrow.gif (94 bytes) LUSAS Programmable Interface (LPI)

  General information
green_arrow.gif (94 bytes) Hardware specification
green_arrow.gif (94 bytes) Licencing and Networking options
green_arrow.gif (94 bytes) Software prices
green_arrow.gif (94 bytes) Documentation
green_arrow.gif (94 bytes) Links page
 

Request information

 


innovative | flexible | trusted

LUSAS is a trademark and trading name of Finite Element Analysis Ltd. Copyright 1982 - 2022. Last modified: March 07, 2023 . Privacy policy. 
Any modelling, design and analysis capabilities described are dependent upon the LUSAS software product, version and option in use.